Scope of Work

1) Protective maintenance coating application to the Clinton Reservoir Water Treatment Plant, High Service Pumping Station No.2

2) Clinton Reservoir Water Treatment Plant Sludge Room Repairs

When did the project start and complete?

Spring 2019

What service was performed?

Surface preparation, 3-coat epoxy system applied to walls, pumps, motors, piping, and valves.